1.24GWh! Sungrow Supplies Europe's Largest Operational Energy Storage Project
On November 2, BW ESS announced that Phase I of the Hams Hall battery energy storage project in North Warwickshire, UK, had entered commercial operation. Phase I has a capacity of 350MW/1243MWh. By energy capacity, it is currently the largest operational energy storage system in Europe. And the record is set to rise further. Once Phase II is completed, Hams Hall will expand to 400MW/1424MWh.

From energisation to commercial operation in just 20 days
Hams Hall is located northeast of Birmingham, adjacent to National Grid's Hams Hall 400kV substation. BW ESS said the project took just 20 days from energisation to complete commissioning, testing and entry into commercial operation.
But that "speed" refers specifically to the post-grid-connection phase. It is not the full construction timeline. Construction of Hams Hall began in October 2024, and the 20-day figure refers to the final stage between system energisation and commercial operation.
BW ESS also said the project was built and commissioned within budget and entered operation ahead of schedule. Sungrow, Energy-IO, National Grid and the UK's National Energy System Operator, NESO, were among the partners involved in project delivery.
Phase II to add another 181MWh
Following the commissioning of Phase I, Hams Hall will continue to expand. Phase II will add another 50MW of power and 181MWh of capacity, taking the full project to:
- Power: 400MW
- Capacity: 1424MWh
- Duration: 3.56 hours
According to BW ESS, at full capacity Hams Hall can store enough electricity to supply around 1.3 million homes for up to 3.5 hours, roughly equivalent to the total number of households across Greater Manchester.
How do you convince banks to lend to a 1GWh project?
Whether a battery project can be built is an engineering question. How it makes money after completion, whether revenues can cover debt, and whether investors are willing to hold the asset over the long term are what ultimately determine whether the project can become an infrastructure asset.
At this scale, it is becoming increasingly difficult to rely on a simple "future arbitrage revenues" story when speaking to banks. Hams Hall has gradually brought together a long-term optimisation agreement, revenue protection, debt financing and equity capital.
▍First, put a floor under revenues
On April 28, 2026, BW ESS signed a 10-year floor and optimisation agreement with EDF.
EDF will optimise Phase I of Hams Hall through its PowerShift platform, dispatching the battery based on electricity supply and demand, market prices and grid requirements. EDF also said Hams Hall is the longest-duration battery storage project it has contracted to date.
The purpose of the agreement is to reduce the project's exposure to electricity price and power market volatility.
▍Then bring in the banks
On October 22, BW ESS announced that Hams Hall had secured debt financing. OCBC, Rabobank and Société Générale will provide the financing on an equal basis, with Rabobank also acting as facility agent.
More than 30 lenders were approached during the financing process. That suggests GWh-scale battery storage is already entering the project evaluation pipelines of a significant number of international banks.
▍Finally, add equity capital
Hams Hall is also not wholly owned by BW ESS. It forms part of the Ardenham storage portfolio jointly owned by BW ESS and AIP Management. The portfolio has a total capacity of around 2.6GWh and also includes the operational Bramley project and the Berkswell project currently under construction.
In September 2025, AIP agreed to acquire a 49% stake in the portfolio. BW ESS retained a 51% majority interest and continues to be responsible for construction and operations. AIP is an energy transition infrastructure investor backed by Storebrand and has invested more than €8 billion in infrastructure assets.
By bringing in AIP, BW ESS did not give up control of the project, but it secured a source of long-term equity capital and shared part of the capital burden and ownership risk associated with a GWh-scale project.
So Hams Hall is not relying entirely on post-commissioning peak-valley arbitrage revenues. Before commercial operation, it had already put in place a long-term optimisation agreement, revenue protection, equity capital and debt financing. The project's engineering delivery and commercial structure were, in effect, closed out in parallel.
Final thoughts
Hams Hall is also one of Sungrow's largest energy storage projects in Europe. In 2024, Sungrow announced that it would supply around 1.4GWh of PowerTitan 2.0 liquid-cooled energy storage systems for the project, involving 280 units, and said the systems were designed with grid-forming capability. The November 2 commercial operation announcement once again listed Sungrow as a key project partner.
Viewed in the context of Europe's large-scale storage market, what makes Hams Hall particularly notable is that three things have come together at the same time: more than 1GWh of operational capacity at a single site, a duration of around 3.5 hours, and the completion of long-term commercial agreements, equity funding and debt financing before commercial operation.
Competition in Europe's large-scale storage market is no longer only about equipment pricing and installed capacity. How large a project can be built, whether duration matches market demand, whether revenues are protected by long-term agreements, and whether banks and infrastructure funds are willing to commit capital are all becoming decisive factors in whether projects actually get built.
For GWh-scale storage, having enough equipment is now only the starting point. The real threshold is whether grid connection, operations, contracts and financing can be brought together so that every MWh of capacity becomes a cash flow that banks can underwrite and long-term investors are willing to hold.
Featured News
All News →
Data Centers Cannot Wait for Grid Connections—Aggreko Puts 1MW Battery Storage on Trailers
Aggreko has added three trailer-mounted BESS products to its North American fleet, including two 1MW systems aimed at construction sites and data centers awaiting grid capacity. With roughly one hour of usable storage, the units are designed for transitional power, load support and hybrid operation rather than long-term grid replacement.

CATL Delivers First 8-Hour EnerQB Systems for Quinbrook's 24GWh Australian Pipeline
CATL and Quinbrook Infrastructure Partners have completed production and delivery of the first EnerQB long-duration energy storage systems. Designed for eight-hour discharge, the initial units will undergo a 12-month trial at Stanwell Power Station in Queensland, Australia. Quinbrook has identified a potential 3GW/24GWh project pipeline, although wider deployment will depend on trial results, financing, grid connections and subsequent procurement.

BNEF's Q4 Energy Storage Tier 1 List Shrinks 26% to 50 Manufacturers
BloombergNEF has named 50 manufacturers to its Q4 2026 Tier 1 Energy Storage list. Based on publicly available company disclosures, Energy Planet has confirmed 19 of the manufacturers and compiled historical inclusion records for 12 of them. While a single appearance shows that a supplier met the criteria for that quarter, repeat inclusion offers a stronger indication of its ability to maintain a pipeline of qualifying projects. Tier 1 remains a measure of market adoption, however, rather than a product-quality ranking, corporate credit rating or substitute for project-level technical and financial due diligence.

From 110 kV Rejection to 400 kV Approval: What Local Capabilities Do BESS Projects Need in Poland?
Poland's energy storage market is attracting a growing number of equipment manufacturers, developers and investors, but entering the market is not the same as delivering a project. In an Energy Planet webinar, CORVION P.S.A. CEO Mariusz Balicki drew on project experience, including a grid connection that shifted from a rejected 110 kV route to an approved 400 kV route and an ageing wood-processing plant that cut its energy costs by more than 30%, to explain how local teams contribute to grid analysis, system design, financial modelling, certification and long-term delivery.

Risen Energy Marks 18 Years in Australia with Two HJT Module Launches
Risen Energy has marked 18 years in Australia with the launch of two HJT modules targeting different segments of the country's solar market. The 760 Wp Hyper-ion Ultra is designed for utility-scale projects, while the 500 Wp, 23.5%-efficient RisenSpace targets residential and commercial rooftops and carries 40-year product and performance warranties. The Melbourne anniversary event also highlighted Risen Energy's research partnership with UNSW on low-silver metallisation, ultra-thin silicon wafers and lower-carbon module-frame technologies.

Up 350%: Utility-Scale Battery Additions Overtake Residential Storage in Germany
Germany commissioned more than 500,000 battery storage systems totalling approximately 8.2 GWh in the first nine months of 2026. Utility-scale additions surged by around 350% to 3.8 GWh, overtaking residential storage and signalling a shift from household solar support towards grid-scale flexibility.

Dutch Home Storage Policy Boost: Government Moves to End "Double Taxation"
The Dutch government is exploring ways to prevent energy tax from being charged twice on electricity stored and re-exported by home batteries and V2G systems, although the metering rules and implementation timeline remain undecided.

Sonnen Files for Insolvency Two Months After Shell Sale
German home battery and virtual power plant pioneer Sonnen has filed for insolvency roughly two months after Shell sold the group to investment firm Tiven. Service for more than 150,000 existing customers is expected to continue, while parts of the group may be restructured or wound down. Sonnen's US operation, meanwhile, is reporting higher sales and production, pointing to a sharp regional divide.