U.S. Utility Launches 800MW Energy Storage Procurement in One Go
Another major energy storage procurement round is underway in the United States. Recently, Appalachian Power (APCo) officially launched two energy storage solicitations, seeking to procure a combined up to approximately 800MW of energy storage resources. However, this 800MW does not represent a single 800 MW standalone storage project, nor does it simply mean that APCo is purchasing 800MW of storage power plants all at once. According to the latest information published on its official website, this procurement has actually been divided into two parts:
- Up to 500MW of energy storage through a PSA (Purchase and Sale Agreement)
- Up to 300MW of energy storage through a CPA (Capacity Purchase Agreement)
The 500MW PSA explicitly accepts both new-build projects and existing energy storage facilities, while the 300MW CPA is open to eligible energy storage resources in the PJM region that meet the relevant capacity qualification requirements. The bid deadline for both solicitations is September 30, 2026. What Appalachian Power is doing this time is not simply "buying energy storage," but simultaneously testing two different energy storage procurement models.

500MW to Buy Assets, 300MW to Buy Capacity
Let's first look at the 500MW portion. Appalachian Power plans to procure up to 500MW of energy storage resources through one or more PSAs. Such agreements typically involve the acquisition of project assets, with the core structure being the purchase of 100% of the equity interests in a project company. Both new-build projects and existing energy storage facilities are eligible to participate. Therefore, the 500MW portion is closer to a model of "buying projects and assets."

The other 300MW is completely different. This portion uses a Capacity Purchase Agreement, meaning APCo does not necessarily need to acquire the storage facility itself. Instead, it obtains the capacity that the energy storage project can provide through a contractual arrangement.

Therefore, from a commercial-model perspective, this 800MW procurement is actually divided into two different routes: one involves acquiring the energy storage asset itself, while the other involves purchasing the capacity provided by the energy storage resource.
For a utility, directly owning an energy storage asset versus purchasing storage capacity involves different levels of investment, asset risk, operational responsibility, and cost recovery. And Virginia's latest policy framework specifically requires utilities to evaluate both approaches.
Why Procure Through "Both Models"?
According to the latest Virginia Code, relevant electric utilities are required to use a competitive procurement process for energy storage. More importantly, the law explicitly requires utilities, during the procurement process, to solicit both proposals for purchasing energy storage capacity and proposals for purchasing the energy storage facilities themselves.
Utilities must then compare different proposals based on factors including cost, risk allocation, asset ownership, and impacts on customers. Therefore, the 500MW PSA + 300MW CPA structure actually corresponds to two different asset and commercial models.
One asks, Who will own the storage project?" The other asks, "If I do not own the project, can I purchase the capacity it provides?" Energy storage is increasingly being treated like a conventional power resource and is being incorporated into a more mature utility procurement framework.
780MW of Short-Duration Storage, Followed by Another 520MW of Long-Duration Storage
Under Virginia's latest energy storage policy, Appalachian Power, as a Phase I Utility, will need to further expand its energy storage resources.
▍The first category is short-duration energy storage
By December 31, 2040, the utility must seek the necessary approval from the SCC to construct, acquire, or procure 780MW of short-duration energy storage capacity. Under the regulatory definition, short-duration storage refers to energy storage resources with a duration of less than 10 hours at rated power.
▍The second category is long-duration energy storage
By the end of 2045, the utility must seek the necessary approval from the SCC to construct, acquire, or procure 520MW of long-duration energy storage capacity. Half of this capacity must have the relevant regulatory application submitted by the end of 2035.
The 520MW is further divided. Half of the storage capacity must have a duration of 10–24 hours, while the other half must have a duration of more than 24 hours.
In other words, based solely on the targets explicitly set out in the current legislation, the short-duration and long-duration energy storage requirements applicable to Appalachian Power already add up to 1.3GW.
If the long-duration storage targets are formally implemented, Appalachian Power will need to move beyond conventional 2-hour and 4-hour storage, extending its procurement requirements to 10–24-hour and even more-than-24-hour long-duration storage.
Conclusion
Some may wonder: Virginia requires Appalachian Power to advance 780MW of short-duration energy storage resources by the end of 2040, and the utility has now launched solicitations totaling roughly 800 MW. Does that mean the target is essentially being completed in a single procurement round?
Not exactly. The roughly 800MW figure is simply the combined target capacity currently announced under the two RFPs. The final amount of projects selected and the total MW ultimately contracted will depend on the bid results and subsequent regulatory approvals.
At the same time, 800MW refers only to power capacity. The final MWh capacity of each project, its storage duration, and how much of it ultimately qualifies toward Virginia's short-duration energy storage target will depend on the specific project proposals and subsequent regulatory determinations.
The questions facing large U.S. utilities are now moving one step further. Who should own an energy storage asset? Should the utility purchase and own it directly, or should it purchase only the capacity? How should the costs and risks of different models be compared? And for storage lasting more than 10 hours, or even more than 24 hours, how should these resources be procured?
This solicitation has put these questions squarely on the table. Energy storage procurement by U.S. utilities is gradually moving beyond simply "building a batch of storage" and toward a broader power-resource procurement framework centered on asset ownership, capacity value, and long-duration storage capabilities.
🔗 Full RFP documents: https://energyplanet.global/post/84?v=20260818-nuxt-og-v1
Featured News
All News →
Italy Opens 16GWh Storage Auction Today as Second MACSE Round Expands by 60%
Italy will open its second MACSE energy storage auction on 24 November, procuring up to 16GWh of capacity from new projects scheduled for delivery in 2029. Compared with the first auction, procurement volume has increased by 60%, while the maximum permitted bid has been reduced from €37,000/MWh/year to €27,000/MWh/year. The results will provide a new indication of competition, regional deployment and current cost levels in Italy's energy storage market.

The Real Test Comes When the Grid Goes Down: 1,000 Witness MWh-Scale Diesel–Battery Microgrid Demonstration
A live MWh-scale demonstration at Sungrow GEPS 2026 showcased how battery storage, diesel generation and grid-forming technology can work together to deliver reliable power in off-grid applications. ENERGY PLANET joined the event to explore the technical highlights and their implications for future C&I energy storage projects.

Tesla Launches 7.4MW Powercore: Connecting Batteries Directly to the 34.5kV Grid and Medium Voltage to 800V Data Centres
Tesla has launched Powercore, a solid-state medium-voltage platform integrating transformer, bidirectional inverter and circuit-breaker functions. Rated at 7.4MW, it connects 800V–2,000V DC systems with 10kV–34.5kV AC networks, targeting battery storage, solar and 800V AI data centres. The first units are scheduled to operate in 2027, although Tesla has not disclosed pricing, customers or initial projects.

UPS Moves to the Grid Edge as Vertiv Launches 3 MVA Medium-Voltage System
Vertiv has launched the 3 MVA PowerNexus MV UPS, moving UPS functionality from the indoor low-voltage side to the outdoor 34.5kV grid connection point. Designed for new and expanding AI data centres, the system integrates fault ride-through, AI load smoothing, power-quality control and one-to-four-hour battery backup. Following a proof-of-concept demonstration in Bologna, commercial shipments are expected to begin in mid-2027.

Envision Gen 8 Selected for 442 MWh Grid Forming BESS in Germany Taking Partnership Close to 600 MWh
Envision Energy and German storage developer ju:niz Energy are advancing the 442 MWh Smareg 13 project in Bavaria. The four-hour, grid-forming development is planned next to the operational Smareg 12 site, while public records currently show a 100 MW/401 MWh configuration and a March 2028 target date.

CATL Delivers First 8-Hour EnerQB Systems for Quinbrook's 24GWh Australian Pipeline
CATL and Quinbrook Infrastructure Partners have completed production and delivery of the first EnerQB long-duration energy storage systems. Designed for eight-hour discharge, the initial units will undergo a 12-month trial at Stanwell Power Station in Queensland, Australia. Quinbrook has identified a potential 3GW/24GWh project pipeline, although wider deployment will depend on trial results, financing, grid connections and subsequent procurement.

1.24GWh! Sungrow Supplies Europe's Largest Operational Energy Storage Project
BW ESS’s Hams Hall project in the UK has officially brought its first phase online, with 350MW/1.243GWh of capacity, making it the largest operational battery storage project in Europe. Sungrow supplied the BESS, with Energy-IO and other partners involved in project delivery. The project also secured a 10-year optimisation agreement with EDF, debt financing from international banks and equity investment from AIP, highlighting the full value chain behind Europe’s GWh-scale storage projects, from equipment supply and project delivery to commercial operations and financing.

BNEF's Q4 Energy Storage Tier 1 List Shrinks 26% to 50 Manufacturers
BloombergNEF has named 50 manufacturers to its Q4 2026 Tier 1 Energy Storage list. Based on publicly available company disclosures, Energy Planet has confirmed 19 of the manufacturers and compiled historical inclusion records for 12 of them. While a single appearance shows that a supplier met the criteria for that quarter, repeat inclusion offers a stronger indication of its ability to maintain a pipeline of qualifying projects. Tier 1 remains a measure of market adoption, however, rather than a product-quality ranking, corporate credit rating or substitute for project-level technical and financial due diligence.