Got Approval but Still Not Started Construction? SSE Upgrades Its Energy Storage Project from 2 Hour
On August 13, SSE Renewables announced that its revised proposal for the Mullafarry energy storage project in County Mayo, northern Ireland, had officially received planning approval. After the modification, the project scale will reach 80MW/320MWh.
Interestingly, the project's power capacity has actually remained unchanged at 80MW. The real change is the storage capacity, which has been directly increased from the previous 160MWh to 320MWh, meaning the duration of the energy storage system has been extended from the original 2 hours to up to 4 hours.

Before Construction Even Started, the Project Was Upgraded from 2 Hours to 4 Hours
As early as April 2025, SSE had already obtained planning permission. At that time, the project was planned as an 80MW/160MWh system, capable of continuous charging and discharging for around 2 hours. SSE stated at the time that the stored electricity from the system would be equivalent to supplying more than 75,000 households with power for approximately two hours.
Under the normal project development process, obtaining planning approval would typically be followed by moving ahead with construction. However, SSE did not proceed directly according to the original design. More than a year later, SSE decided to revise the project plan. In June 2026, the company submitted a new planning application to the local authority, adjusting the project to:
80MW/320MWh, with a maximum storage duration of 4 hours. The power capacity remained unchanged, but the energy capacity was doubled.
- Original plan: 80MW/160MWh, 2 hours
- New plan: 80MW/320MWh, 4 hours
Why was the project changed to 4 hours? When SSE submitted the modification application in June this year, the company explained that the change was made partly in response to the latest developments in energy storage technology, and partly because electricity system operators are seeing increasing demand for reliable and flexible power reserve capacity.
Previously, many storage projects were designed around a 2-hour duration. However, the current expectation is that storage systems should be able to store more electricity at once and provide support to the grid for a longer period. Therefore, the key purpose of this upgrade is not to make the energy storage system "discharge more powerfully", but to enable it to "discharge for a longer duration".
Four Hours Matches Ireland's Current Energy Storage Policy Direction
In recent years, Ireland has been continuously increasing the role of energy storage in its power system. In July 2024, the Irish government officially released the country's first Electricity Storage Policy Framework, formally integrating energy storage into future electricity system planning.
Ireland aims to achieve 80% of electricity demand being supplied by renewable energy by 2030. However, as wind and solar power continue to grow, having more renewable generation alone is not enough. How to store electricity when generation is high and release it when supply is insufficient has naturally become increasingly important. As a result, the role of energy storage has also grown.
Interestingly, one point in the storage policy framework closely aligns with the upgrade of Mullafarry. In Action 6 of the policy framework, Ireland clearly proposed advancing the procurement of long-duration energy storage services. Relevant storage systems should be capable of continuously supplying electricity to the transmission system for 4 hours or more.
Later, in October 2025, Ireland’s transmission system operator EirGrid further launched a consultation on long-duration energy storage procurement mechanisms, beginning to explore how storage systems of 4 hours and above could be formally incorporated into procurement arrangements.
It should be noted that SSE did not state that the project modification was specifically intended to participate in this long-duration energy storage procurement mechanism. However, judging from the storage duration alone, the direct upgrade from 2 hours to 4 hours is clearly aligned with Ireland's current energy storage development direction.
Moreover, Ireland is not simply issuing policy documents without further action. In June this year, Ireland further eased restrictions on energy storage. The Commission for Regulation of Utilities (CRU) adjusted transmission network charging rules for storage systems, aiming to make it easier for storage assets to participate in wholesale electricity markets. At the same time, the long-duration energy storage procurement framework continues to move forward.
Looking at this series of developments, Ireland's current goal is clear: as wind and solar capacity continues to expand, the country not only needs energy storage to participate more actively in electricity markets, but also needs more storage resources capable of supporting the power system continuously for several hours.
Against this background, SSE's decision to upgrade Mullafarry from a 2-hour project to a 4-hour project before construction even began becomes much less surprising.
Located Next to SSE's Existing 104MW Power Station
From a location perspective, Mullafarry is not an entirely independent new site. The project will be built on SSE-owned land, directly adjacent to the company's existing 104MW power station. If SSE ultimately decides to move forward with construction, the latest official announcement estimates that the construction period will take up to approximately two years.
However, it is important to note that receiving planning approval does not mean the project will immediately enter the construction phase. SSE clearly stated in its announcement that whether Mullafarry will ultimately proceed to construction still depends on the company’s Final Investment Decision (FID).
The revised proposal has already received planning approval, but information regarding the final construction timeline, equipment suppliers, battery cell technology selection, and specific commissioning schedule has not yet been further disclosed by the company.
Final Thoughts
When SSE first obtained planning permission in 2025, Mullafarry was still an 80MW/160MWh, 2-hour energy storage project. By 2026, before the project had even officially started construction, SSE had already redesigned the system and increased the storage capacity directly from 160MWh to 320MWh. Moreover, Mullafarry is not the only project undergoing this type of adjustment.
In Sweden, the Vaggeryd project was originally approved with a storage capacity of 200MWh. Ingrid later submitted a new permit application, doubling the capacity to 400MWh. The revised project scale became 100MW/400MWh, corresponding to a 4-hour energy storage system.
In Northern Ireland, the UK, ABO Energy is also redesigning an already approved 140MW, 2-hour Coolkeeragh energy storage project into a 140MW, 4-hour system. One project may simply be an individual case. However, when similar adjustments begin appearing in Ireland, Sweden, and Northern Ireland, this trend deserves closer attention.
In the past, 2-hour energy storage systems were a common configuration for many large-scale projects. But now, project developers are clearly reconsidering a fundamental question: For future energy storage projects, what duration will actually be the most suitable?
Featured News
All News →
Italy Opens 16GWh Storage Auction Today as Second MACSE Round Expands by 60%
Italy will open its second MACSE energy storage auction on 24 November, procuring up to 16GWh of capacity from new projects scheduled for delivery in 2029. Compared with the first auction, procurement volume has increased by 60%, while the maximum permitted bid has been reduced from €37,000/MWh/year to €27,000/MWh/year. The results will provide a new indication of competition, regional deployment and current cost levels in Italy's energy storage market.

The Real Test Comes When the Grid Goes Down: 1,000 Witness MWh-Scale Diesel–Battery Microgrid Demonstration
A live MWh-scale demonstration at Sungrow GEPS 2026 showcased how battery storage, diesel generation and grid-forming technology can work together to deliver reliable power in off-grid applications. ENERGY PLANET joined the event to explore the technical highlights and their implications for future C&I energy storage projects.

Tesla Launches 7.4MW Powercore: Connecting Batteries Directly to the 34.5kV Grid and Medium Voltage to 800V Data Centres
Tesla has launched Powercore, a solid-state medium-voltage platform integrating transformer, bidirectional inverter and circuit-breaker functions. Rated at 7.4MW, it connects 800V–2,000V DC systems with 10kV–34.5kV AC networks, targeting battery storage, solar and 800V AI data centres. The first units are scheduled to operate in 2027, although Tesla has not disclosed pricing, customers or initial projects.

UPS Moves to the Grid Edge as Vertiv Launches 3 MVA Medium-Voltage System
Vertiv has launched the 3 MVA PowerNexus MV UPS, moving UPS functionality from the indoor low-voltage side to the outdoor 34.5kV grid connection point. Designed for new and expanding AI data centres, the system integrates fault ride-through, AI load smoothing, power-quality control and one-to-four-hour battery backup. Following a proof-of-concept demonstration in Bologna, commercial shipments are expected to begin in mid-2027.

Envision Gen 8 Selected for 442 MWh Grid Forming BESS in Germany Taking Partnership Close to 600 MWh
Envision Energy and German storage developer ju:niz Energy are advancing the 442 MWh Smareg 13 project in Bavaria. The four-hour, grid-forming development is planned next to the operational Smareg 12 site, while public records currently show a 100 MW/401 MWh configuration and a March 2028 target date.

CATL Delivers First 8-Hour EnerQB Systems for Quinbrook's 24GWh Australian Pipeline
CATL and Quinbrook Infrastructure Partners have completed production and delivery of the first EnerQB long-duration energy storage systems. Designed for eight-hour discharge, the initial units will undergo a 12-month trial at Stanwell Power Station in Queensland, Australia. Quinbrook has identified a potential 3GW/24GWh project pipeline, although wider deployment will depend on trial results, financing, grid connections and subsequent procurement.

1.24GWh! Sungrow Supplies Europe's Largest Operational Energy Storage Project
BW ESS’s Hams Hall project in the UK has officially brought its first phase online, with 350MW/1.243GWh of capacity, making it the largest operational battery storage project in Europe. Sungrow supplied the BESS, with Energy-IO and other partners involved in project delivery. The project also secured a 10-year optimisation agreement with EDF, debt financing from international banks and equity investment from AIP, highlighting the full value chain behind Europe’s GWh-scale storage projects, from equipment supply and project delivery to commercial operations and financing.

BNEF's Q4 Energy Storage Tier 1 List Shrinks 26% to 50 Manufacturers
BloombergNEF has named 50 manufacturers to its Q4 2026 Tier 1 Energy Storage list. Based on publicly available company disclosures, Energy Planet has confirmed 19 of the manufacturers and compiled historical inclusion records for 12 of them. While a single appearance shows that a supplier met the criteria for that quarter, repeat inclusion offers a stronger indication of its ability to maintain a pipeline of qualifying projects. Tier 1 remains a measure of market adoption, however, rather than a product-quality ranking, corporate credit rating or substitute for project-level technical and financial due diligence.