Muchea Battery

Oceania > Australia > Western Australia Utility-scale BESS

Project Overview

UGL is appointed by Neoen and Tesla to build the 164 MW / 905 MWh Muchea Battery northeast of Perth, Western Australia. It is Neoen’s first 6-hour long-duration storage facility, deploying 252 Tesla Megapack 2XL units. UGL’s scope covers site preparation, design & construction of a 132kV substation, HV infrastructure, control and switchroom facilities, earth...

LocationOceania > Australia > Western Australia
CategoryUtility-scale BESS
CompanyNeoen; Tesla; UGL
Power164.00
Capacity905.00