Baotou Weijun 1.5GW / 9GWh Grid-side Independent Energy Storage Demonstration Project

Asia > China > Inner Mongolia Autonomous Region Utility-scale BESS

Project Overview

At 00:08 on June 21, 2026, the project’s 500 kV collector substation was officially connected to the grid and commissioned. The milestone completed the project’s end-to-end power transmission pathway, enabling electricity from the five 220 kV energy storage stations to be stepped up and delivered to the western Inner Mongolia power grid. Source: http://nm.p...

LocationAsia > China > Inner Mongolia Autonomous Region
CategoryUtility-scale BESS
CompanyHyperStrong, Mingyang, Chuangqi, and Wolong (four leading Chinese energy storage companies, each responsible for constructing a designated section of the project).
Power (MW)1500
Capacity (MWh)9000
Commissioned Date2026-06-21